Capacity Increase And Quality Improvement Of Gole Gohar Pelletizing Plants (Plants I & II)
Previous slide
Next slide
Project SummaryCurrent StatusProject TimelineProject Status
Gole Gohar Company Has Planned to Increase The Capacity of Pelletizing Plants From 5.5 to 7 Mt/Y Along With Improvement of Product Quality.
In Order To Achieve These Goals, Local and European Engineering Firms Have Come Together. The PC Contractor, Nazmavarane Sanat O Madan Company was also Responsible for Detailed Design Verification. This part of the contract was handed over to RFK.
The Actual Engineering Progress is about 90%, The Foundation Construction of Main Equipment and Project Deliverables Procurement is Started.
The Project Started in October 2022 And It is Planned to Be Done by March 2025.