CHADORMALOU Transfer And Storage Of Iron Concentrate Project

Previous slide
Next slide
Project Summary

ARDAKAN Pelletizing Plant Has an Open Storage Area of Iron Concentrate. The Maximum Wind Velocity in that area is 148 Km/h, Within 10-20 Meters From The Ground Level.

In order to prevent the loss of Iron Ore Concentrate, as a short-term solution Molasses was Used which was not effective. As a long-term solution Covered Storage for Concentrate Was Proposed by the Client.

4 Silos and Mixers were Designed to Enhance the Quality of Concentrate by Mixing Different Concentrate and Monitoring the Humidity.

Current Status

Waiting for the Client Signal to start the Contractor Selection Bid.

Project Timeline

Design Project Started in August 2021 and Completed in March 2021. Contactor Selection Tender Documents Submitted by RFK at That Time and Construction Duration is Foreseen to be About 18 Months After the Effective Date of Contact.

Project Status

Chadormalou Mining and Industrial Company

Client

Basic and Detailed Design, Responsible for Contactor Selection, Tender Services, and Site Supervision.

RFK Role

Chadormalou Industrial Complex, near Ardakan City, Yazd Province.

Location

Iron Concentrate

Feed Specification