Blain Increases Of Iron Concentrate Of BAFGH IRON ORE Project

Previous slide
Next slide
Project Summary
Current Status

In Operation.

Project Timeline

Start February 2018, Handover to Client, July 2020.

Project Status

Azaran Company

Client

Bafgh Iron Ore Complex in Bafgh City, Yazd Province

Location

Iron Concentrate which is K80<90 μ, Humidity<7%, Blain=1100

Feed Specification

Iron Concentrate Sizing K100<100 Microns, Humidity<7%, Blain=1800

Product Specification

5 MT/Y (Dry Basis)

Plant Capacity